Snoqualmie Falls Bank Stabilization

Snoqualmie river hero
Snoqualmie overview

Overview

Location: Snoqualmie, WA

Project Type: Shoreline & Waterways

Application: Riverbank Stabilization

Product Used: ARMORMAX

Snoqualmie river problem

Problem

In 2009, Puget Sound Energy began a comprehensive upgrade of the hydroelectric infrastructure at Snoqualmie Falls – a power generation facility built in 1890. Loose soils and heavy rainfall contributed to a landslide along the Snoqualmie River bank in the Fall of 2010, and geotechnical engineers was commissioned to provide a long-term design solution.

Snoqualmie 02

Solution

ARMORMAX® 75 was used to stabilize the bank in 2013, and a full array of native vegetation was designed as a natural solution to stabilize the bank.

Snoqualmie perform

Performance

ARMORMAX will provide permanent erosion protection for up to 75 years, outlasting other slope reinforcement methods.

Interested in learning more about Armormax®?

View Product